Kathmandu: Nepal has received approval to import up to 350 MW of electricity from India during the winter to meet domestic demand amid lower hydropower generation and damage to several projects caused by recent floods.
India’s Central Electricity Authority (CEA), under the Ministry of Power, has authorized the Nepal Electricity Authority (NEA), the state-owned power utility, to procure electricity through the Indian Energy Exchange (IEX) at competitive rates for up to 17 hours a day, according to NEA officials.
The approval is valid from November 17, 2026, to July 31, 2027. It will allow Nepal to manage the seasonal gap between domestic electricity demand and generation, NEA Managing Director Dirghayu Kumar Shrestha said.
Under the approval, Nepal can import 300 MW through the Kataiya-Kushaha, Ramnagar-Surajpura, and Raxaul-Parwanipur transmission lines. The remaining 50 MW can be imported through the New Nautanwa-Mainahiya transmission line.
Nepal relies heavily on run-of-the-river hydropower projects, resulting in seasonal variations in electricity generation. Higher river flows during summer allow the country to generate surplus electricity for export, mainly to India. However, lower water levels during winter reduce domestic generation and increase the need for imports.
The power supply situation has also been affected by damage to hydropower projects in central Nepal during the Rasuwa-Bhotekoshi floods in August. Projects with a combined installed capacity of 431 MW remain disconnected from the national grid following the floods.
Domestic electricity generation is expected to improve from mid-April as river water levels rise. This could reduce the country’s reliance on imported electricity and allow exports to resume, officials said.